This browser is not actively supported anymore. For the best passle experience, we strongly recommend you upgrade your browser.
NEWS & ARTICLES NEWS & ARTICLES

NEWS & ARTICLES

| 5 minutes read

The Minimum Performance Principle and the Calculation of Damages for Breach of Contract

Written by: Paul Stocco, Partner & Heather Cave, Student-At-Law 

In breach of contract cases, one of the key legal issues is calculation of damages suffered by the non-defaulting party. The typical rule is that damages are awarded so as to give the non-defaulting party the benefit that it would have enjoyed from the contract had the contact been fully performed. Contracts sometimes contain limitation of liability clauses that restrict and clarify the types and amounts of damages that can be claimed by and awarded to a non-defaulting party. However, there are also instances where the calculation of damages is less clear. For example, when there are alternative ways of performing the contract at issue, and where the alternative ways of contractual performance give rise to different damages calculations, a Court will choose the scenario that is least profitable to the non-defaulting party and least burdensome to the defaulting party. This is known as the “minimum performance principle”, and this principle has been recognized since the Supreme Court of Canada’s decision in Hamilton v Open Window Bakery.  In the recent decision in the case of Atos IT Solutions and Services GMBH v Sapient Canada Inc., the Ontario Court of Appeal confirmed that this principle is alive and well.

The Atos case involved a contractual dispute between a prime contractor, namely Sapient Canada Inc. (“Sapient”) and its subcontractor Altos. Sapient was contracted by Enbridge Gas Distribution Inc. to replace its existing software systems. In turn, Sapient subcontract Altos to perform two different types of services in relation to this project: (i) data conversion (“DC”) services, and (ii) application management support (“AMS”) services.

The completion of the work was delayed, and Sapient terminated its subcontract with Altos for cause. Altos disputed the termination. In its action against Sapient, Altos claimed damages for loss of profits. The trial judge determined that the contract had been wrongfully terminated and awarded damages in favour of Altos. On appeal, Sapient challenged the damages.

The subcontract at issue included two different termination provisions. Under the first clause (the “DC Termination Provision”), Sapient had a right to terminate the DC services “for convenience”. Under this clause, damages for termination of the DC services for convenience would be calculated on the basis of a specific formula. By contrast, the second termination clause allowed Sapient to terminate the entire subcontract “for cause”. Under this second termination clause, damages were calculated differently than under the first termination clause.  

Given that Sapient had terminated the subcontract “for cause”, the trial judge held that the damages calculation under the DC Termination Provision (the “for convenience” termination clause), did not apply. As a result, the damages award for the termination of the subcontract was greater than it would have been had the DC Termination Provision damages formula applied.

In its appeal of the damages award, Sapient argued that under the “minimum performance principle”, it didn’t matter which termination clause was relied on. Sapient argued that the minimum performance principle dictated that the less onerous “for convenience” formula should have been applied. The Court of Appeal agreed.

As the Court of Appeal explained, the basic principle underlying damages for breach of contract is that damages are compensatory. The defaulting party is only required to pay damages in an amount that puts the non-defaulting party in the position it would have been in had the contract been fully performed. Put another way, damages are designed to give the non-defaulting party the benefit that it was expecting from the contract.

However, where the defaulting party has more than one option as to how it might have chosen to perform the contract, damages are assessed on the assumption that the defaulting party would have chosen the option that is least onerous to it rather than the option that is most beneficial/most profitable to the non-defaulting party. If, for example, a contract required a party to supply goods in an amount ranging from 800-1200 tonnes, the minimum performance principle holds that damages for breach of that contract would be assessed on the basis that only 800 tonnes would have been supplied.

The Court of Appeal also held that it was immaterial that Sapient had terminated the subcontract in bad faith[1]. Breaches of a contractual duty of good faith do not affect the principle that damages must be measured in accordance with the minimum performance principle. Even where a defaulting party is found to have acted in bad faith in its termination of a contract, a non-defaulting party cannot recover more than what it would have been entitled to had the defaulting party only complied with its least onerous requirements under the contract.

 As a result of the decision in Atos, parties entering into contracts should bear in mind that if they want to secure for themselves a particular method of performance, and if they want to avoid the application of the minimum performance principle, then the contract must be clear and unequivocal that only one method of performance is contemplated. Otherwise, the minimum performance principle is likely to apply to restrict the damages for breach of contract to the least onerous option available to the defaulting party.

The Court in Atos also dealt with a contractual limitation of liability clause. Sapient relied on the clause at issue to argue that it exclude the “loss of profits” claimed by Altos as a result of the termination of the contract. The Court of Appeal undertook a contextual review of the wording in the clause at issue. The Court of Appeal determined that the exclusion did not apply so as to prevent Altos from claiming loss of profits flowing from the termination of the contract.   

The Altos decision is relevant for the construction industry for a number of reasons. Firstly, construction contract typically have alternative modes of performance. For example, a construction contract may have both a “contract time” (e.g. start date and substantial performance date) and a “construction schedule” that aren’t always the same. In the event of a termination by an owner, it is possible that a contractor’s damage claim for loss of profits could be calculated differently depending on whether the construction schedule or the contract time is used. The “minimum performance principle” dictates that the scenario that is least burdensome to the defaulting party and least beneficial to the non-defaulting party will be used. Secondly, as the limitation of liability clause at issue in Atos is a common one, the Court of Appeal’s decision reminds parties that the wording of any limitation of liability clause should be precise and clearly worded in order for it to be enforceable. Lastly, though much has been written in respect of the Bhasin decision and whether it fundamentally changed contract law, the Court of Appeal confirmed that breaches of a contractual duty of good faith or braches of a common law duty of honest performance do not impose a higher measure of damages.

 [1] The Court of Appeal discussed the recent Supreme Court of Canada decision in Bhasin. The Court of Appeal held that although the Bhasin decision recognized the organizing principle of good faith contractual performance and a common law duty of honest performance of contractual obligations, the Bhasin decision did not supplant the minimum performance principle and its application to the calculation of damages.